The MoSCoW method sorts work into four groups: Must have, Should have, Could have and Won't have (this time). It was built for software projects with a fixed deadline, but it works just as well for a personal project, a house move or a busy week: anywhere you have more to do than time to do it.
This guide covers where MoSCoW comes from, what each letter really means (including the often-muddled W), a worked example, and how to set it up in dypt with tags.
Where the MoSCoW method comes from
MoSCoW is usually credited to Dai Clegg, who developed it at Oracle in the 1990s. It became the standard way to prioritise in DSDM, an agile project framework now looked after by the Agile Business Consortium.
The name is just the four letters M, S, C and W, with two o's added to make it easy to say. It has nothing to do with Moscow.
What each letter means
The definitions below follow the Agile Business Consortium's guide.
- Must have. Without these, the project fails or can't go ahead. DSDM describes them as the minimum the project guarantees to deliver. Ask: "If this were left out, would we cancel or delay?" If the answer is no, it's not a Must.
- Should have. Important but not vital. Leaving it out would be painful, but the result still works.
- Could have. Wanted or nice to have, but less important. These are the first things to drop when time runs short.
- Won't have this time. Things everyone agrees won't be done in this timeframe. They're not rejected for ever, just not now.
The W causes the most confusion. You'll sometimes see it written as "Would like to have", which makes it sound like a fifth level of nice-to-have. It isn't. The W is a decision: this is out of scope for now. Writing it down is useful, because it stops the same ideas creeping back in halfway through.
The rule that keeps it honest
MoSCoW only works if most of the work isn't a Must. DSDM's guidance is that Must haves should typically be no more than about 60% of the effort, with around 20% as Could haves that can be dropped if things overrun.
That buffer is the point. If everything is a Must, there's nothing to drop when the deadline gets close, and the method stops helping.
A worked example
Here's a made-up example: moving house in four weeks.
| Task | Group | Why |
|---|---|---|
| Book the removal van | Must | No van, no move |
| Redirect your post | Must | Important letters would go missing |
| Pack the kitchen | Must | You can't move without packing |
| Sell the old sofa | Should | Saves moving it, but you could take it with you |
| Repaint the spare room before moving in | Could | Nice to have; easier when the room's empty |
| Re-tile the bathroom | Won't (this time) | A project for next year |
Three Musts, one Should, one Could and one Won't. If week three goes badly, the repainting goes first, and nobody is surprised.
Common mistakes
- Everything is a Must. Then nothing is. Push hard on each Must: would the project really fail without it?
- Treating Won't as "maybe later". A Won't is a decision for this timeframe. Write it down so it doesn't sneak back in.
- No timeframe. MoSCoW sorts work against a deadline or a time box. Without one, Should and Could blur together.
- Never revisiting. Priorities change. Review the groups when something big changes, not just at the start.
How to do the MoSCoW method in dypt
dypt has four priority levels (High, Mid, Low and none), but MoSCoW is clearer with tags, because the letters mean something specific.
- Make a parent task for the project. For example, "Move house". Give it a deadline: MoSCoW needs a timeframe.
- Create four tags:
must,should,couldandwont. Add one to each task under the project. - Filter by tag to see one group at a time. Start with
must. When the Musts are done or under way, move toshould. - Keep the Won'ts. Don't delete them; leave them tagged
wontso the decision is written down. Next time you plan, filter forwontto see what was parked. - Optionally, match priority too. If you also want MoSCoW to show up when you sort by priority, set Musts to High, Shoulds to Mid and Coulds to Low.
If a Must feels too big to start, use dypt's AI task breakdown to split it into smaller steps. If you're working with others, you can share the project with them. You can read more about custom tags and priorities, deadlines and reminders on their feature pages.
Try it on your next project
Pick one project with a deadline. Sort every task into Must, Should, Could or Won't this time, then check that the Musts are well under two-thirds of the work. If they're not, push some down.
If you'd like the groups, the deadline and the breakdown in one place, try it in dypt, free to start.
Sources and further reading
- Agile Business Consortium, "What is MoSCoW prioritisation?": the definitions and the effort guidance, from the body that maintains DSDM.
- The ABC method: the ABCDE version: a similar idea for a daily list, ranking tasks by their consequences.
- The Eisenhower matrix: sorting by urgency and importance instead.